Maggie’s Centre, St Bartholomew’s Hospital

Previous slide
Next slide

Contract summary

Works involved Construction of a single basement with a 2 storey RC frame within St Bart’s Hospital.

Basement works excavation, sheet pilings, drainage. Concrete to slab, pits, beams, walls, columns to the high tolerance requirements for the glass cladding system.

Grade 3 Waterproofing to underside of slab & walls. Design and installation of all formwork. Reinforcement and continuity reinforcement. Installation of foul water pumping chambers. Installation of in-situ concrete stairs including helical exposed concrete feature stairs.

Contract in Brief

Market sector
Health

Scope of works
Substructure & Superstructure

Main contractor
Sir Robert McAlpine Ltd

Engineer
Arup

Architect
J M Architects

Duration
36 weeks

Value
£1.6m

Contract start date
July 2016