Maggie’s Centre, St Bartholomew’s Hospital

Contract in Brief

Market sector

Health

Scope of works

Substructure & Superstructure

Main contractor

Sir Robert McAlpine Ltd

Engineer

Arup

Architect

J M Architects

Duration

36 weeks

Value

£1.6m

Contract start date

July 2016

Contract Summary

Works involved Construction of a single basement with a 2 storey RC frame within St Bart’s Hospital.

Basement works excavation, sheet pilings, drainage. Concrete to slab, pits, beams, walls, columns to the high tolerance requirements for the glass cladding system.

Grade 3 Waterproofing to underside of slab & walls. Design and installation of all formwork. Reinforcement and continuity reinforcement. Installation of foul water pumping chambers. Installation of in-situ concrete stairs including helical exposed concrete feature stairs.