Wimbledon AELTC
Contract in Brief
Market sector
Commercial
Scope of works
Wimbledon AELTC
Main contractor
Sir Robert McAlpine Ltd
Engineer
Thornton Tomasetti
Architect
KSS
Duration
18 weeks
Value
£1.5m
Contract start date
January 2016
Contract Summary
Installation of concrete pile cap foundations & RC Super-columns to support the steel work for the new roof on court number 1.
Structural alterations to facilitate large diameter piling operations for super column pile caps, works required breaking out the existing slabs, drainage diversions, demolition of existing walls and suspended ceilings. Protection of existing works and surround environment.
Re-instatement of the same finishes with new materials of existing walls, stairs etc. once works completed.
Due to the sensitive location of the site RCE had to ensure that a minimum amount of disruption was caused to the neighbouring properties.