Skip to content

Kettering, Northamptonshire

Contract in Brief

Market sector

Commercial

Scope of works

Crane Bases and Test Slabs

Main contractor

Sir Robert McAlpine

Engineer

SRM Design Group

Architect

SRM Design Group

Duration

12 weeks

Value

£420k

Contract start date

July 2019

Contract Summary

Installation of 4no crane bases, Crane Test slab, Drainage & utilities installation.

 

Works included:

Installation of 600mm diameter CFA Piles, Pilling attendance.

Excavation to formation level

Positioning of all 4 Crane masts to all crane bases.

Installation of reinforcement in all 4 Crane bases

Casting Concrete to Crane Bases.

Excavation and Installation of RC crane test slab.