Highgate Cemetery
Contract in Brief
Market sector
Private
Scope of works
Groundworks & Concrete
Main contractor
Craig Hamilton
Engineer
Frank W Haywood & Associates
Architect
Craig Hamilton
Duration
10 weeks
Value
£150k
Contract start date
September 2015
Contract Summary
Groundworks, Piling & Concrete Works for a new Mausoleum at Highgate Cemetery.
The Groundworks scope included, enabling works, excavation, bored concrete piles, construction of reinforced concrete pile caps and a waterproof concrete slab. The structure also had an in-situ concrete vaulted roof which was constructed using bespoke falsework.