GSK Ware – Hertfordshire
Contract in Brief
Market sector
Commercial
Scope of works
Substructure & Superstructure
Main contractor
MACE
Engineer
Ross & Partners
Architect
Simons
Duration
26 weeks
Value
£1.95m
Contract start date
February 2014
Contract Summary
Works associated with reducing levels, forming mass concrete pad foundations, Drainage, Ground Floor slab and concrete topping to hollow rib decking on upper floors. Works also involved forming of a watertight concrete underpass, including associated temporary works.