18-20 Grosvenor St – W1

Contract in Brief

Market sector

Commercial, Retail

Scope of works

Substructure & Superstructure

Main contractor

Sir Robert McAlpine

Engineer

Ramboll UK

Architect

Flanagan Laurence

Duration

32 weeks

Value

£2m

Contract start date

May 2013

Contract Summary

The project involves the unification of two existing buildings to create a single high quality unit.

Works included underpinning of existing structures, temporary works, bulk excavation, construction of a RC basement, waterproofing, builderswork, drainage and composite concrete flooring.